Campus Life

HUB-Robeson expansion project on schedule

Steel beams are lifted into place for the HUB expansion project, seen from the ground floor of the project. Credit: Annemarie Mountz / Penn State. Creative Commons

UNIVERSITY PARK, Pa. – Overall work on the HUB-Robeson Center expansion project is continuing on schedule, as members of the project executive committee saw during a tour of the construction site last week.

The project includes more than 106,000 square feet of improvements – encompassing about 54,800 square feet of new space and 52,000 square feet of renovated space, all of which results from a recommendation issued by the student-led Facilities Fee Committee at University Park. The project will enhance opportunities for the nearly 1,000 student organizations at University Park, even as it improves accessibility and architecture of the building from the east and HUB Lawn sides.

Erection of the 500 tons of steel for the project continues as the new addition is taking shape. Work also continues in existing areas of the building, including the food court area, mechanical room areas, bookstore and other various interior areas. Much of the work being done now is related to infrastructure support of the building, such as plumbing, electrical and ductwork installation, as well as pouring of new concrete floors and installation of floor tiles. Work also is beginning on the bookstore facades. Passers-by may notice that some of the exterior concrete walls of the bookstore section now are blue, as the walls are being waterproofed and prepared for their terra cotta and brick finishes.

Work on the food court and entry to the HUB Parking Deck will be completed this August, while the bookstore space is expected to be done in time to move the bookstore back into its permanent retail space in October. The entire project is expected to be completed by April 2015.

The project includes more than 106,000 square feet of improvements — encompassing about 54,800 square feet of new space and 52,000 square feet of renovated space. The project also will enhance the accessibility and architecture of the building from the east and HUB Lawn sides.

Plans include a new mezzanine in the Penn State Bookstore and a green roof above it, which will offer space for outdoor seating. A two-story, multipurpose flex theater, meeting rooms and a THON retail store will be added in the building near the HUB parking deck entrance. A more prominent location for student leadership and activities also will be created.

Trustees approved construction of the project at a cost of $44.6 million in May 2013. The project will be paid for primarily from student facilities fees, HUB-Robeson Center reserves, Food Services funds and bookstore reserves.

Follow the project's progress on the Union and Student Activities website, Facebook page and Twitter account.

Last Updated July 8, 2014

Contact